Overview of the building’s development, April 2023
Structure of the first elevated component in foreground, April 2023
Relating the scale of the interior spaces and the ring gallery that connects the entire building, April 2023
The foundations start to reveal the full extent of the building, March 2023
The primary steel structure is complete on the Event Space and nearly complete on the first home, March 2023
Component 1 Level 1 slab concrete pouring, October 2022
Component 1 view from North-West corner, September 2022
Component A foundation work almost complete, September 2022
Component 1 double-height Event Space, September 2022
Component 1 Cellar Level progress, September 2022
Component A slab on grade concrete pouring, August 2022
Component 1 structural steel complete, Component A foundation progress, and elevated components piling works, August 2022
Component 1 structural steel progress, July 2022
Sculptural stair mock-up in American walnut, July 2022
Sculptural stair mock-up in mahogany, July 2022
First structural steel elements erected in Component 1, June 2022
Sculptural stair mock-up steel structure, May 2022
Component A slab on grade progress, April 2022
Component A foundation wall rebar and formwork progress, February 2022
Mirror glass façade visual mock-up, February 2022
Component 1 foundation wall formwork, November 2021
Component 1 foundation wall rebar, November 2021
Foundation concrete progress, July 2021
Foundation rebar progress, May 2021
Subcellar excavation complete, April 2021
Subcellar excavation in progress, March 2021
Support of excavation works, January 2021
Groundbreaking ceremony, December 2020
Construction begins, December 2020
Site preparation, June 2020